The Textomur system was chosen because it could re-use the cohesive material won on site. A 3m bench was formed in the 60° face at an approximate elevation of +4m to provide access for maintenance of the grassed face and for later planting with tree pits up to 1m diameter. The 2,300m2 of Textomur was constructed in 8 weeks, including the placement of some 23,000m3 of silty clay fill.
|